1/10 Net 90 at a glance
- Type
- Early-payment discount
- Discount
- 1% if paid within 10 days
- Full amount due
- 90 days after the invoice date
- Cost of skipping the discount
- 4.6% a year simple, 4.7% compounded
- Also written
- 1/10 n/90, 1% 10 net 90
1/10 Net 90 calculator
- Pay by this date for the 1% discount
- Sunday, Jan 25, 2026 (weekend)
- Pay $9,900, saving $100
- Full amount due
- Wednesday, Apr 15, 2026
- Pay $10,000
Dates count calendar days from the invoice date. Suppliers may define a term differently in their contract; their wording wins.
Example dates
| Invoice dated | Discount until | Full amount due | Days |
|---|---|---|---|
| Jan 15, 2026 | Jan 25, 2026 | Apr 15, 2026 (Wednesday) | 90 |
| Feb 27, 2026 | Mar 9, 2026 | May 28, 2026 (Thursday) | 90 |
| Dec 18, 2026 | Dec 28, 2026 | Mar 18, 2027 (Thursday) | 90 |
What the discount is worth
| Invoice | Discount | Pay early |
|---|---|---|
| $1,000 | $10 | $990 |
| $10,000 | $100 | $9,900 |
| $100,000 | $1,000 | $99,000 |
Skipping the discount buys 80 more days to pay, at a cost of 1% of the invoice: 4.6% a year as a simple rate (1/99 × 365/80), or 4.7% compounded.
Average amount owed to the supplier
Paying on the due date, about 90 days after the invoice date on average.
| Annual spend with the supplier | Average owed | Compared with Net 30 |
|---|---|---|
| $250,000 | $61,644 | +$41,096 |
| $1,000,000 | $246,575 | +$164,384 |
| $5,000,000 | $1,232,877 | +$821,918 |
Setting up 1/10 Net 90 in your ERP
- Business Central
- Due Date Calculation 90D; Discount Date Calculation 10D, Discount % 1
- Xero
- Bills due 90 day(s) after the invoice date
- NetSuite
- Term with Days Till Net Due 90, % Discount 1, Days Till Discount Expires 10
QuickBooks Online and Sage Intacct also store payment terms with a due rule. Whether an early-payment discount is applied to the bill automatically differs by product (Sage Intacct AP terms can carry one; Xero terms set due dates only), so check the bill's due date and amount after setting up a new term.
What it means
1/10 Net 90 is a supplier payment term with two dates. Pay within 10 days of the invoice date and you can deduct 1%. Miss that window and the full invoice amount is due in 90 days. You will also see it written as 1/10 n/90 or 1% 10 net 90.
The clock starts on the invoice date, not the day the invoice reaches your desk and not the statement date. The term does not count from month end. That matters when an invoice is dated Thursday, Jan 15, 2026 but does not arrive until the following week. The discount deadline is still tied to Jan 15.
The discount is small on a single invoice and easy to dismiss. On a $1,000 invoice the discount is $10, so paying early costs $990. On a $10,000 invoice the discount is $100, so paying early costs $9,900. The decision is not really about the $10. It is about whether the cash you free up by waiting 80 more days is worth more than the 1%.
Working out the dates
Take the invoice date and add 10 calendar days for the discount deadline. Add 90 calendar days for the full amount due. Use the actual invoice date printed on the document. If your ERP stores a received date, do not use it as the start date for 1/10 Net 90.
An invoice dated Thursday, Jan 15, 2026 gives a discount until Sunday, Jan 25, 2026. The full amount is due Wednesday, Apr 15, 2026. A payment by Sunday, Jan 25, 2026 can take the 1%. After that date, the full amount is due Wednesday, Apr 15, 2026.
An invoice dated Friday, Feb 27, 2026 gives a discount until Monday, Mar 9, 2026 and the full amount is due Thursday, May 28, 2026. An invoice dated Friday, Dec 18, 2026 gives a discount until Monday, Dec 28, 2026 and the full amount is due Thursday, Mar 18, 2027. Put both dates on the payment proposal so the clerk sees the discount date and the net date side by side.
Some discount dates land on a Sunday, such as Sunday, Jan 25, 2026. The term still gives that date. If your payment run falls after it, the discount is gone.
Is the discount worth taking?
The headline number is the cost of giving up the discount. If you skip the 1% and keep the cash for 80 more days, the simple annual cost is 4.6% and the compounded annual cost is 4.7%. Compare that with your own cost of funds. If your borrowing cost is below 4.6%, taking the discount can look attractive. If it is above, the arithmetic may point the other way.
On a $100,000 invoice the discount is $1,000, so paying early costs $99,000. That is real cash out the door 80 days sooner. The question is whether the $1,000 saving is worth the earlier payment. For a controller, the answer can differ by supplier and by month.
The cash flow effect of Net 90 is large. With $250,000 a year of spend with one supplier, about $61,644 is owed on average, $41,096 more than on Net 30. With $1,000,000 a year of spend, about $246,575 is owed on average, $164,384 more than on Net 30. Those balances are why some buyers treat 1/10 Net 90 as a financing choice rather than a data entry field. If you take the discount, you are paying 80 days early to save 1%.
Where these invoices go wrong
The first failure is keying the wrong term. A clerk sees 1/10 Net 90 and enters 1/10 Net 30 because Net 30 is the default in the vendor record. The invoice then sits in a queue that ignores the 90 day due date. The next payment run treats it as late or due, and the discount date can be missed because the system is working from the wrong terms. Check the term on the vendor record against the printed invoice before you approve the payment run.
The second failure is counting from the received date instead of the invoice date. An invoice dated Thursday, Jan 15, 2026 has a discount until Sunday, Jan 25, 2026. If the clerk starts the count from the day the invoice arrives, the payment can land after Jan 25 while still claiming the 1%. The supplier sees a short payment and the buyer sees a credit balance that never clears.
A third failure is taking the discount after the window. A payment made after Sunday, Jan 25, 2026 on a Thursday, Jan 15, 2026 invoice is a full amount payment, not a discounted one. If AP deducts 1% anyway, the supplier either rejects the short payment or posts a small credit that sits on the account. The same account can then get paid again when a statement shows the invoice as open. That is how paying a statement as well as the invoice creates a duplicate. The statement is not a new invoice.
The fourth failure is paying a re-sent invoice twice. Vendors resend invoices when a payment is late or when a clerk asks for a copy. If the second copy goes through the normal queue, it can be paid as a new invoice. On a $1,000 invoice with a $10 discount, you now have two $990 payments against one $1,000 invoice. Match on invoice number, invoice date and amount before you release a second payment. If the vendor record shows the invoice already paid, stop and check the payment history.
Questions
What does 1/10 Net 90 mean on an invoice?
It means you can take a 1% discount if you pay within 10 days of the invoice date. If you do not, the full amount is due in 90 days. It is also written as 1/10 n/90 or 1% 10 net 90.
How do I work out the discount date for 1/10 Net 90?
Start with the invoice date and add 10 calendar days. For an invoice dated Thursday, Jan 15, 2026, the discount date is Sunday, Jan 25, 2026. Do not count from the date you received the invoice or from month end.
What is the cost of skipping the 1% discount on 1/10 Net 90?
You give up 80 days of credit. The simple annual cost is 4.6% and the compounded annual cost is 4.7%. Compare that with your own cost of funds before you decide.
Can I take the 1/10 Net 90 discount after 10 days?
No. The discount applies only if payment is made by the discount date, which is 10 days from the invoice date. After that, the full amount is due in 90 days. A later payment that deducts 1% will usually be treated as a short payment.
Updated Nov 13, 2026. Figures on this page are calculated by ERPSav from the definitions shown. The explanatory text is drafted with AI from those figures and checked automatically before it is published. General information only, not legal, tax or financial advice.